Brideswell Blog

2005: Feb | Mar | April | May | June | July | Aug | Sept | Oct | Nov | Dec     2006: Jan

 

Thursday, July 4, 2005

Day 148

ESB errected ESB pole just inside gateway.



Thursday, July 7, 2005

Day 151

Guy came to put steel bars in dormer windows to support them.

 


Monday, July 11, 2005

Day 155 Groundwork

Groundwork started, electricity duct from new ESB pole at road to where the esb box at the side of house will be located. Water pipe and power cable for submersible pump from well to house buried. These run back to the garage where out 150 litre pressure tank will be located. This will provide pressure to bot the hot and cold water systems.


Tuesday, July 12, 2005

Day 156 Groundwork & Plumbing first fix

Plumber started first fix. Trench started for heat array this runs from back of garage for 150 metres down into marshland behind the house. The wet ground will be a good conductor for the geothermal energy into the collector pipe. There are actually 2 trenches side by side in a L shape. They will have 300meters of pipe in each.

 


Wednesday, July 13, 2005

Day 157 Groundwork & Plumbing first fix

Plumber continued work. Work on trench continued.


Thursday, July 14, 2005

Day 158 Blocklaying & Plumbing first fix

Plumber continued work. Work on groundwork continued. Blocklayer number 3 started work on the house.


Monday, July 18, 2005

Day 162 Blocklaying & Well drilling

Blocklayers continued work. Well drilling began.

 

 

Groundwork continued.

 


Tuesday, July 19, 2005

Day 163 Well Drilling

Well drilling finished.