Thursday, July 4, 2005
Day 148
ESB errected ESB pole just inside gateway.
Brideswell Blog |
2005: Feb | Mar | April | May | June | July | Aug | Sept | Oct | Nov | Dec 2006: Jan
ESB errected ESB pole just inside gateway.
Guy came to put steel bars in dormer windows to support them.
Groundwork started, electricity duct from new ESB pole at road to where the esb box at the side of house will be located. Water pipe and power cable for submersible pump from well to house buried. These run back to the garage where out 150 litre pressure tank will be located. This will provide pressure to bot the hot and cold water systems.
Plumber started first fix. Trench started for heat array this runs from back of garage for 150 metres down into marshland behind the house. The wet ground will be a good conductor for the geothermal energy into the collector pipe. There are actually 2 trenches side by side in a L shape. They will have 300meters of pipe in each.
Plumber continued work. Work on trench continued.
Plumber continued work. Work on groundwork continued. Blocklayer number 3 started work on the house.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
Blocklayers continued work. Well drilling began.
![]() |
![]() |
![]() |
![]() |
Groundwork continued.
![]() |
![]() |
![]() |
![]() |