Thursday, June 2, 2005

Day 116 Dormer Windows

Dormer window frame designed.


Friday, June 10, 2005

Day 124 Timberframe

Timberframe completed.


Wednesday, June 15, 2005

Day 129 Blocklaying

 

A blocklayer finally turned up to do our garage. Woohoo!

 


Thursday, June 16, 2005

Day 130 Roofing

 

Roofer arrived to start work on batons and felt.

 




 


Friday, June 17, 2005

Day 131 Roofing

 

Roofer finished work on batons and felt.

Wednesday, June 22, 2005

Day 136 Blocklaying / Electrics

 

Blocklayer number 2 finished garage. Electrician began first fix.

Thursday, June 23, 2005

Day 137 Electrics

 

Electrician stopped working on first fix until the plumber does his work.

Friday, June 24, 2005

Day 138 Blocklaying

 

Blocklayer number 2 started blocks on house.

Monday, June 27, 2005

Day 141 Blocklaying

 

Blocklayer number 2 didn't arrive back to work on house.

Tuesday, June 28, 2005

Day 142 Blocklaying

 

Blocklayer number 2 didn't arrive back to work on house, didn't answer phone, hung up when we called him from a different number and he realised who was calling.