Wednesday, Thursday March 2nd, 3rd 2005

Days 22, 23

The blockie returned and put in the foundation for the garage.

 


Sunday March 6th 2005

Day 26

Laura and T.J. put in the kingspan insulation.

 


Sunday March 20th 2005

 

Day 41

Laura and T.J. put in the insulation that had blown off in the meantime.


Wednesday March 23rd 2005

Day 44

Plumber put in ground floor underfloor heating arrays in zones for each room downstairs.

 

 


Tuesday, Wednesday March 29th, 30th 2005

Days 50, 51

T.J. put down the sole plates for the timber frame.

 

 