Saturday, Oct 1, 2005

Day 238 Fuinneogs

 

T.J. and Martin put in the rest of the glass in the windows.


Monday, Oct 3, 2005

Day 240 Plastering

Plasterers continued work on outside of garage, continued skimming upstairs rooms.


Friday, Oct 14, 2005

Day 251 Electrics

Electricians started 2nd fix .

 


Saturday, Oct 15, 2005

Day 252 Paint Party no. 1

 

T.J., Laura, Karen and Martin started the first coat painting upstairs.


Tuesday, Oct 18, 2005

Day 255 2nd fix electrics/Plumbing

Plumber put in shower trays and bath. Electricians continued 2nd fix.

 


Wednesday, Oct 19, 2005

Day 256 2nd fix carpentry/Fascia and Soffit

Fascia and Soffit finished apart from dormer windows. Carpenter started work.

 


Thursday, Oct 20, 2005

Day 257 2nd fix carpentry

Carpenter continued work.


Friday, Oct 21, 2005

Day 258 Plastering / 2nd fix carpentry

Plasterers plastered chimney breasts inside house. Carpenter put in skirting and architraves.


Saturday, Oct 22, 2005

Day 259 Paint party no. 2

Laura, TJ, Wendy, Megan, Tracey, Mick T and Murt painted most of downstairs first coat. 2nd fix carpenter continued work, put in stira attic stairs.